Construction Update – December 21, 2022
Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale:
Work Accomplished This Week:
Building A
▪ Began courtyard brick installation
▪ Continued exterior perimeter window replacement work
▪ Continued wood trim installation on 3ʳᵈ Floor units
▪ Continued finishing drywall on 2ⁿᵈ Floor
▪ Continued layout and framing of kitchen area
▪ Continued layout and framing of amenity spaces on 1ˢᵗ Floor
▪ Continued infilling CMU on 1ˢᵗ Floor
▪ Continued masonry walls in the mechanical room
▪ Continued sprinkler rough-in work on 1ˢᵗ Floor units
▪ Completed underground storm piping in the courtyard
▪ Completed equipment pads in the mechanical room
Building B
▪ Began tile install on 4E
▪ Began hanging drywall on 4N & 4W units
▪ Began fire lid on 1N & 1W
▪ Continued hanging drywall 2E
▪ Continued balcony door install
▪ Continued amphitheater retaining wall
▪ Continued sprinkler rough-in on 3N & 3W
▪ Continued HVAC & electrical rough-in work on 2N & 2W
▪ Continued EIFS, fiber cement on North and East elevations
▪ Continued stone veneer installation on the East wing
▪ Completed ceiling framing and rough-ins on 4N & 4W units
▪ Completed gypcrete on 2E apartments and corridor
Here are pictures of the construction that took place over the last week:
*Photos courtesy of Wohlsen Construction.