Construction Update – December 7, 2022

Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale:

Work Accomplished This Week:

Building A

▪ Complete setting balcony posts
▪ Continued finishing drywall on 2nd floor
▪ Continued mechanical & electrical rough-ins, in the first floor
apartments
▪ Continued exterior perimeter window replacement work
▪ Completed unit entry door frames
▪ Continued hanging fan coil units on first floor
▪ Continued aqua flash and EIFS insulation in the courtyard
▪ Continued infilling cmu on the first floor
▪ Pizza oven was delivered
▪ Began EPDM on pool roof
▪ Began footings for balcony turndowns
▪ Began excavation for trash room drain and underground
plumbing in the mechanical room
▪ Began setting patio doors in the courtyard

Building B

▪ Received cabinet delivery for 4E apartments
▪ Continued finishing drywall on 3E
▪ Continued finishing drywall & received drywall delivery for ceilings on 2E
▪ Completed in wall insulation & sprinkler rough in on 4N & 4W
▪ Continued HVAC & electrical rough-ins on 3N & 3W
▪ Continued EIFS, fiber cement, and flashing windows
▪ Began hanging fire lid on 2N & 2W
▪ Began EPDM on patio balcony roofs in the courtyard
▪ Began prepping for balcony doors
▪ Began stone veneer on the east wing
▪ Began installing prehung doors & trim on 4E

Here are pictures of the construction that took place over the last week:

*Photos courtesy of Wohlsen Construction.