Construction Update – February 23, 2023

Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale:

Work Accomplished This Week:

Building A

▪ Began elevator retrofit work
▪ Began wood trim in 1ˢᵗ floor units
▪ Began sound isolation ceiling
▪ Continued exterior perimeter EIFS replacement work
▪ Continued balcony framing & composite decking
▪ Continued brick veneer in the courtyard
▪ Continued EIFS & fiber cement installation in the courtyard
▪ Continued patio door installation on the outer perimeter
▪ Continued ceramic tile installation on 3ʳᵈ floor
▪ Continued unit kitchen casework on 3ʳᵈ floor
▪ Continued MEP rough-in amenity spaces on 1ˢᵗ floor
▪ Completed trim in 2ⁿᵈ floor units
▪ Completed finishing drywall in 1ˢᵗ floor units
▪ Completed priming in 1ˢᵗ floor units

Building B

▪ Began MEP finishes in 4E units
▪ Began wood trim in 3N units
▪ Began hanging drywall on 1N & 1W
▪ Continued stone veneer installation in the courtyard
▪ Continued plumbing finishes & glass shower doors on 4E
▪ Continued kitchen backsplash tile on 4E units
▪ Continued ceramic tile on 3E & 2E
▪ Continued installing unit casework on 3E & 2E
▪ Completed remaining gypcrete in common areas
▪ Completed prime and first coat of paint on 3N & 3W
▪ Completed finishing drywall 2N & 2W units
▪ Completed above-ceiling rough in the first floor

Site

▪ Began carport footings in east parking area
▪ Completed carport footings in the south parking area

Here are pictures of the construction that took place over the last week:

*Photos courtesy of Wohlsen Construction.