Construction Update – February 27, 2023

Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale:

Work Accomplished This Week:

Building A
▪ Began installing unit furnaces on 3E
▪ Began wood trim 1st floor units
▪ Began hanging drywall in office spaces on 1st floor
▪ Continued ceramic tile installation on 3rd floor
▪ Continued exterior perimeter EIFS replacement work
▪ Continued balcony composite decking
▪ Continued brick veneer in the courtyard
▪ Continued elevator retrofit work
▪ Continued EIFS & fiber cement installation in the courtyard
▪ Continued MEP rough-in amenity spaces on 1st floor
▪ Completed interior framing in the pool

Building B
▪ Began installing unit furnaces on the 4th floor
▪ Began exterior caulk around windows and doors
▪ Began hanging drywall ceilings in 1E units
▪ Began installing gutters at the roof level
▪ Began ceramic tile on 4N & 4W
▪ Continued MEP finishes in 4E units
▪ Continued wood trim in 3N & 3W units
▪ Continued ceramic tile 2E
▪ Continued installing unit casework 2E and received
delivery for 4W
▪ Completed ceramic tile in bathrooms on 3E
▪ Completed sanding 2N & 2W to prepare for primer
▪ Completed hanging drywall on walls 1N & 1W units
▪ Completed stone veneer installation in the courtyard

Site
▪ Completed carport footings in East parking area
▪ Continued site lighting

Here are pictures of the construction that took place over the last week:

*Photos courtesy of Wohlsen Construction.