Construction Update – July 7, 2022
Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale:
Building A:
▪ Began sanitary line on east side
▪ Began Juliette balcony steel installation
▪ Began existing EIFS removal on South side
▪ Continued window and door blocking on 2ⁿᵈ and 3ʳᵈ floor
▪ Continued DWV piping and duct installation on 2ⁿᵈ and 3ʳᵈ floor
▪ Continued underground plumbing on 1ˢᵗ floor
▪ Completed courtyard footings
Building B:
▪ Began wood framing on north wing
▪ Continued CMU walls in elevator #3 and #4 and stair tower C
▪ Continued plumbing rough ins on east wing
▪ Completed wood framing on 4ᵗʰ floor of east wing
▪ Completed steel framing on game room and vestibule