Construction Update – June 13, 2022
Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale:
Building A:
- Completed underground plumbing in bathrooms 115 & 116
- Continued footings in courtyard
- Continued framing interior walls on 2nd floor
- Continued DWV piping installation
- Continued hanging duct on 3rd floor
- Began installing electrical back boxes
- Began saw cutting for underground MEP
Building B:
- Completed wood framing on 3rd floor in east wing
- Continued CMU walls in stair D and elevator #4
- Began slab on grade prep in west wing
- Began work on the waterline out front of building A
- Began plumbing rough on 1st floor