Construction Update – June 13, 2022

Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale:

Building A:

  • Completed underground plumbing in bathrooms 115 & 116
  • Continued footings in courtyard
  • Continued framing interior walls on 2nd floor
  • Continued DWV piping installation
  • Continued hanging duct on 3rd floor
  • Began installing electrical back boxes
  • Began saw cutting for underground MEP

Building B:

  • Completed wood framing on 3rd floor in east wing
  • Continued CMU walls in stair D and elevator #4
  • Began slab on grade prep in west wing
  • Began work on the waterline out front of building A
  • Began plumbing rough on 1st floor

 