Construction Update – June 27, 2022
Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale:
Building A:
- Began duct installation on 2nd floor
- Began window framing on 3rd floor
- Continued DWV piping and duct installation on 3rd floor
- Continued saw cutting for underground MEP
- Continued underground plumbing on 1st floor
- Completed skylight openings infill framing and decking
- Completed setting the doghouse manhole in the street
Building B:
- Continued CMU walls in elevator #3 and #4 and stair tower C
- Continued plumbing rough ins on 1st and 2nd floor of east wing
- Continued wood framing on 4th floor in east wing
- Completed installation of conduit from transformer to building B
- Completed porch piers in units 102 and 104 and footings for porches in units 107, 108, 110, 112, 114 and 117