Construction Update – June 6, 2022
Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale:
Building A:
- Began excavating and prepping courtyard footings
- Began framing interior walls in apartments on 2nd floor
- Continued framing interior walls in apartments on 3rd floor
- Continued exterior courtyard framing
- Continued DWV piping installation
- Continued hanging duct on 3rd floor
Building B:
- Began installation of grease pit
- Continued wood framing on 3rd floor in east wing
- Continued masonry walls in stair D and elevator #4
- Completed underground plumbing in west wing
- Completed slab on grade pour in north wing
- Completed underground electrical work
Here a few pictures of demolition work over the last week: