Construction Update – March 27, 2023

Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale:

Work Accomplished This Week:

Building A

▪ Began priming amenity spaces
▪ Began FRP in the kitchen area
▪ Began installing light fixtures & GRD’s on 3ʳᵈ floor
▪ Began elevator retrofit work in elevator 2
▪ Began cutting in louvers around the exterior perimeter
▪ Continued LVT in 3ʳᵈ floor units
▪ Continued unit casework on 3ʳᵈ & 2ⁿᵈ floors
▪ Continued ceramic wall tile installation on 1ˢᵗ floor units
▪ Continued exterior perimeter EIFS replacement at stair B
▪ Continued fiber cement installation in the courtyard
▪ Continued installing patio doors around the exterior perimeter
▪ Continued installing balcony decking
▪ Decommissioned the existing boiler pump and started the new
▪ Completed setting unit furnaces on 2ⁿᵈ floor
▪ Completed SOG at the loading dock

Building B

▪ Began wire shelfing in 4ᵗʰ floor units
▪ Began toilet accessories on 4E and 3E
▪ Began LVT flooring in 2E units
▪ Continued kitchen countertop units on 4N & 4W
▪ Continued cabinet install in 2N & 2W units
▪ Continued backsplashes on east wing
▪ Continued ceramic tile in 2N & 2W units
▪ Completed carpet flooring in 4E & 3E units
▪ Completed LVT & carpet in 3E units
▪ Completed ceramic tile on 3N & 3W
▪ Completed wood trim in 3N & 3W units
▪ Completed priming 1E units
▪ Completed sanding 1N & 1W units
▪ Completed stone veneer on west wing and moved back to east wing
▪ Completed setting unit furnaces on 3ʳᵈ floor

Site

▪ Completed loading dock slab pour
▪ Completed rain leader underground piping outside Building B
▪ Completed new light pole install

Here are pictures of the construction that took place over the last week:

*Photos courtesy of Wohlsen Construction.