Construction Update – May 1, 2023
Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale:
Work Accomplished This Week:
Building A
▪ Began LVT in 1ˢᵗ floor units
▪ Began ceramic tile in the locker room
▪ Continued balcony railings around the exterior
▪ Continued installing brick louvers
▪ Continued elevator retrofit work in elevator 2
▪ Continued unit casework
▪ Continued kitchen backsplashes on 3ʳᵈ floor
▪ Continued carpet in 3ʳᵈ floor units
▪ Continued shower doors in 3ʳᵈ floor units
▪ Continued LVT in 2ⁿᵈ floor units
▪ Continued ceramic tile on 1ˢᵗ floor units
▪ Continued millwork in the pub area
▪ Continued installing commercial kitchen equipment
▪ Continued installing pool equipment
▪ Completed entry vestibule sheathing and air barrier
▪ Completed ceramic tile in common area bathrooms
Building B
▪ Continued LVT in 3N & 3W units
▪ Continued stone veneer on North elevation
▪ Continued balcony railings
▪ Continued balcony vinyl soffits
▪ Continued caulking exterior windows and patio doors
▪ Continued unit kitchen countertops & backsplashes
▪ Continued VCT in mechanical & IT rooms
▪ Continued cabinet install in 1ˢᵗ floor units
▪ Continued wood trim in 1ˢᵗ floor units
▪ Completed storefronts at the game room
▪ Completed vinyl soffits
Site
▪ Completed removing trees along 10ᵗʰ St & Building A
▪ Continued carport framing in south parking area
▪Began stone prep for paving
Here are pictures of the construction that took place over the last week:
*Photos courtesy of Wohlsen Construction.