Construction Update – May 10, 2022
Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale:
Building A
▪ Completed footings and piers at pool area
▪ Completed core drilling plumbing floor penetrations on 3rd floor
▪ Continued removing steel from the courtyard area
▪ Continued framing interior walls on 2nd floor
▪ Continued hauling away debris from demolition
▪ Began exterior courtyard framing on 3rd floor
Building B
▪ Completed waterproofing and concrete pour for elevator 4 pit
▪ Continued footings in the north wing
▪ Continued masonry foundation walls
▪ Continued masonry walls at stair tower D
▪ Continued underground plumbing in North wing
Here a few pictures of demolition work over the last week: