Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale:

  • Continued courtyard demolition
  • Continued framing walls and topping out 3rd Floor of Building A
  • Continued wall layout and framing on 2nd Floor of Building A
  • Continued storm piping & structure install on site
  • Continued footings at Building B
  • Continued hauling away debris from demolition
  • Continued masonry foundation walls at Building B
  • Continued underground plumbing at the East end of Building B
  • Continued foundation walls at South side of Building B
  • Continued foundations at pool area
  • Began waterproofing at poured walls at Building B