Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale:

  • Continued demolition on 1st floor of Building A
  • Continued courtyard demolition at roof level 
  • Continued framing walls on 3rd floor of Building A
  •  Continued storm piping & structure install on site
  •  Continued footings at Building B
  •  Continued crushing concrete from the Bunker building
  •  Continued hauling away debris from demolition
  •  Began masonry foundation walls at East end of Building B
  •  Began underground sanitary at the east end of Building B

To view the demolition at Chestnut Ridge at any time, please visit https://chestnutridgeatrodale.org/events/chestnut-cam/. This bird’s-eye view camera of Chestnut Ridge refreshes when movement is registered, or every few minutes.