Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale:
- Continued demolition on 1st floor of Building A
- Continued courtyard demolition at roof level
- Continued framing walls on 3rd floor of Building A
- Continued storm piping & structure install on site
- Continued footings at Building B
- Continued crushing concrete from the Bunker building
- Continued hauling away debris from demolition
- Began masonry foundation walls at East end of Building B
- Began underground sanitary at the east end of Building B
To view the demolition at Chestnut Ridge at any time, please visit https://chestnutridgeatrodale.org/events/chestnut-cam/. This bird’s-eye view camera of Chestnut Ridge refreshes when movement is registered, or every few minutes.
Check out a few pictures of demolition work over the last week:
![](https://chestnutridgeatrodale.org/wp-content/uploads/2022/04/Masonry-Foundation-Walls.bmp)
![](https://chestnutridgeatrodale.org/wp-content/uploads/2022/04/North-Facade-Demo.bmp)
![](https://chestnutridgeatrodale.org/wp-content/uploads/2022/04/Underground-Sanitary.bmp)