Demolition Update – December 28, 2021

Some of the projects Wohlsen Construction have been working on this week at Chestnut Ridge at Rodale include:

  • Completed site prep for Building B demolition
  • Completed MEP making safe for Building B demolition, including
    disconnecting transformer
  • Continued selective demolition in Building A

If you’d like to view the demolition at Chestnut Ridge at any time, please visit https://chestnutridgeatrodale.org/events/chestnut-cam/. This birds-eye view camera of Chestnut Ridge refreshes when movement is registered or every few minutes.

Please enjoy some of the pictures of demolition from this past week below.