Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale:
- Completed mechanical, engineering, and plumbing demolition on 3rd floor of Building A
- Continued selective demolition on 2nd floor of Building A
- Continued demolition of mechanical equipment
- Continued installation of temporary power and lighting
- Began slab and exterior wall demolition at Building B
- Began demolition of skylight openings on 3rd floor
To view the demolition at Chestnut Ridge at any time, please visit https://chestnutridgeatrodale.org/events/chestnut-cam/. This bird’s-eye view camera of Chestnut Ridge refreshes when movement is registered, or every few minutes.
Check out a few of the the pictures of demolition from this past week:
![](https://chestnutridgeatrodale.org/wp-content/uploads/2022/02/Fulfillment-Building-Demo-700x521.jpg)
![](https://chestnutridgeatrodale.org/wp-content/uploads/2022/02/2nd-Floor-Demo-700x520.jpg)
![](https://chestnutridgeatrodale.org/wp-content/uploads/2022/02/Drone-Footage-2-700x528.jpg)