Demolition Update – February 4, 2022

Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale:

  • Completed mechanical, engineering, and plumbing demolition on 3rd floor of Building A
  • Continued selective demolition on 2nd floor of Building A
  • Continued demolition of mechanical equipment
  • Continued installation of temporary power and lighting
  • Began slab and exterior wall demolition at Building B
  • Began demolition of skylight openings on 3rd floor

To view the demolition at Chestnut Ridge at any time, please visit https://chestnutridgeatrodale.org/events/chestnut-cam/. This bird’s-eye view camera of Chestnut Ridge refreshes when movement is registered, or every few minutes.

Check out a few of the the pictures of demolition from this past week: