Demolition Update – January 14, 2022
Some of the projects Wohlsen Construction have been working on this week at Chestnut Ridge at Rodale include:
- Continued selective demolition in Building A, specific to the third floor
- Completed saw cutting at Building A courtyard column footings
- Equipment was delivered to begin Building B structural demolition
Please enjoy some of the pictures of demolition from this past week below.