Demolition Update – March 28, 2022
Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale:
- Continued demolition on 1st floor of Building A
- Continued courtyard demolition at roof level
- Continued framing walls on 3rd floor of Building A
- Continued storm piping & structure install on site
- Continued footings at the East and North side of Building B
- Continued crushing concrete from the Bunker building
- Continued hauling away debris from demolition
- Masonry contractor mobilized for Building B
To view the demolition at Chestnut Ridge at any time, please visit https://chestnutridgeatrodale.org/events/chestnut-cam/. This bird’s-eye view camera of Chestnut Ridge refreshes when movement is registered, or every few minutes.
Check out a few pictures of demolition work over the last week: