Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale: Building A: ▪ Completed porte cochere steel▪ Continued hanging drywall...
Learn MoreConstruction Update – October 24, 2022
Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale: Building A: ▪ Completed base paving in the west parking area▪ Completed...
Learn MoreConstruction Update – October 14, 2022
Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale: Building A: ▪ Started hanging drywall on East wing of floor 3▪ Started...
Learn MoreConstruction Update – September 26, 2022
Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale: Building A: ▪ Continued MEP rough-in work on floors 1-3▪ Continued...
Learn MoreConstruction Update – September 16, 2022
Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale: Building A: ▪ Continue window removal▪ Begin site electric...
Learn MoreConstruction Update – September 7, 2022
Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale: Building A: ▪ Completed slab pour in kitchen area▪ Completed sprinkler...
Learn MoreConstruction Update – September 1, 2022
Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale: Building A: ▪ Began batt insulation on exterior walls▪ Continued...
Learn MoreConstruction Update – August 25, 2022
Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale: Building A: ▪ Completed demo of cross bracing on 2ⁿᵈ & 3ʳᵈ per...
Learn MoreConstruction Update – August 16, 2022
Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale: Building A: ▪ Began spray foam and exterior sheathing in courtyard▪...
Learn MoreConstruction Update – August 10, 2022
Over the last week, Wohlsen Construction has been working on the following projects at Chestnut Ridge at Rodale: Building A: ▪ Began structural steel installation in pool area▪ Began...
Learn More